9 of October, 17:03

Lugansk thermal power plant resumed operation after an outage
Thermal power plant in Happiness, which provides electricity to most of the Luhansk region resumed work after emergency shutdown, declared on the last working day of the week press service of the Donbass fuel-energy (DTEK).

before in connection with the emergency shutdown of the TPP residents of the North of the Luhansk region remained without electricity.

"Power engineers of DTEK Luganskaya TPP no more than two hours restored the work of the unit? 10 ", - reported in the report.

according to the information DTEK, the problems related to the fact that the Luhansk TPP for more than 1 year disconnected from United power system of Ukraine due to damaged power lines.