<a href=NEWS.rin.ru'><a href=NEWS.rin.ru'> NEWS.rin.ru 
27 of November, 14:58

"Krymtel ": CHP in Kerch will triple the capacity by 10 December
Reed-Burunskaya CHP, which is the only source of providing electricity to Kerch will start after you restore the main turbine by 10 December, thus tripling the generated power, said in Simferopol, 1-St Deputy head of the Board of the organization "Krimtech" Taras a Whole.

Kerch is in a blackout of the Crimea from Ukraine remained in practice without energy. Technically to give electricity to Kerch from the center of the Peninsula At this point in time is not possible, told in " Krymenergo ". 145-strong town is served around 6 megawatts, with one turbine running Reed-Burunskaya CHP. In felt communication failure, water and warmth.

"We plan to launch after the restoration of main turbine Reed-Burunskaya CHP by 10 December. It produces 12 MW of power, " said A.

according to him, common the power plant output after exit recovery will Increase at least to 20 megawatts.

Firm "Krymtel" serves on the Peninsula 3 thermal power plant - Simferopol, Saki and Kamysh-Burunskiy.

yesterday at the Simferopol CHP launched the 2nd turbine generation increasing from 50 to 100 megawatts.

The Crimea in the night of Sunday was completely de-energized because of the erosion in the South Ukraine transmission towers supplying electricity to the Peninsula. In the region introduced a state of emergency until full power is restored. Supporters of the blockade of Crimea on Tuesday allowed the repair crews to begin restoring one of the 4 damaged power lines.

Read more about news of the Crimea

sections: Politics

    Copyright © RIN 2005-